Building project summer work schedule
The district’s construction project is progressing according to schedule, with completion anticipated in 2010. Here’s a summary of the work that will be done over the summer months:

June 2008
  • District awards bids to contractors;

  • Contractors provide detailed plans of summer work to be completed.

June-August 2008

  • Create construction/access road from Route 4 to campus;

  • Set up staging area on campus for construction equipment;

  • Create retention pond and enlarge drainage areas behind Elementary School to prevent flooding;

  • Remove and replace Jr.-Sr. High School roof;

  • Remove and replace Elementary School roof.

If you have any questions on these projects, please feel free to call the Superintendent’s Office at 695-3255, ext. 3242.
 

 
 
 
         
  Schooling Caring Succeeding logo graphicSchooling Caring Succeeding graphic      
column spacer graphic
column spacer graphic This page is maintained by Kim Smithgall, Communications Specialist, according to web publishing guidelines used by the Schuylerville Central School District. All rights reserved. This Web site was produced in cooperation with the Capital Region BOCES Communications Service. The district is not responsible for facts or opinions contained on any linked site. © 2008
column spacer graphic column spacer graphic column spacer graphic