Building Project Timeline

ACTIVITY

START

COMPLETE

Design development

March 2007

Oct. 2007

Construction documents

Oct. 2007

Jan. 2008

State Ed. Dept. approval

Feb. 2008

May 2008

Bid document preparation

June 2008

June 2008

Bidding/contracts

Sept. 2008

Nov. 2008

Construction phase: roof, site work, abatement

June 2008

Oct. 2008

Construction phase: Elementary School addition

April 2009

Aug. 2010

Construction phase: Jr.-Sr. High School classroom addition

May 2009

Jan. 2010

Construction phase: Jr.-Sr. High School locker room addition June 2009 Jan. 2010
Construction phase: Elementary & Jr.-Sr. High School renovations June 2009 Aug. 2010
     
  Schooling Caring Succeeding logo graphicSchooling Caring Succeeding graphic      
column spacer graphic
column spacer graphic This page is maintained by Kim Smithgall and Tara Mitchell, Communications Specialists, according to web publishing guidelines used by the Schuylerville Central School District. All rights reserved. This Web site was produced in cooperation with the Capital Region BOCES Communications Service. The district is not responsible for facts or opinions contained on any linked site. © 2008
column spacer graphic column spacer graphic column spacer graphic